Estimation of Brick Work (Calculation of Construction Materials, Skill & Unskilled labor, Water, Time, & Price)

 


Estimation of Brickwork:

Brickwork is measured in cubic meters and square meters according to the width of the wall. In brickwork, twenty-five to thirty percent of a concrete mixture is considered.

 

Example: Calculate construction materials, water, manpower, Time, & Price for a brick wall that is 10 meters long, 0.35 meters wide, and 2.50 meters high.

Note: the size of a brick 11 x 7 x 23 cm, And the Concrete mix ratio for mortar is 1:6.

More information about construction site location:

The price of one Brick: 0.05 USD.

The price of one cubic Sand is 6.4 USD.

The price of 1 bag of Cement is 4.5 USD.

The price of one liter of water is 0.01 USD.

Wage for Unskilled labor, 5 USD

Wage Skilled labor 13 USD

 

Solutions:

Step 1: Calculation of Construction Materials (Brick, Sand, Cement):

Total Volume of Brick Wall (V) => V= Length x Width x Hight = 10 x 0.35 x 2.5 = 8.75 CuM.

Concrete Mixture (V1) => V1= (25% x V) = (25% x 8.75) = 2.187 Cubic Meter.

Mark Ratio is: 1:6, 1+6=7

Total Cement: 2.187/7 x 1 = 0.312 Cum = 0.312 x 1440 (Cement Density) = 449.24 Kgr,
1 Bag Cement = 50 Krg, So 449.24/50 = 8.98 = 9 Big Cement.

Total Sand: 2.187/7 x 6 = 1.87  Cum Sand

 

Total Brick (V2) => V2=V-V1= 8.75 – 2.187 = 6.563 Cu Meter.

One Brick Volume= 0.11 x 0.07 x 0,23 = 0.00177

Total Bricks = 6.563/0.00177 = 3,708 Bricks + 5% damages = 3708 + 185 = 3893 Bricks.

 

Step 2: Calculation of manpower (Skilled & Unskilled labor):

Skilled Labor for 1 Cum = 0.5 MD
Unskilled Labor for 1 Cum = 1.45 MD

Total Skilled Labor = 8.75 x 0.5 = 4.3 Skilled Labor

Total Unskilled labor = 8.75 x 1.45 = 12.68 Unskilled labor

 

Step 3: Time Calculation:

If you want to complete this work in 2 days (Skilled Labor 4.3/2 = 2.15, Unskilled Labor 12.68/2 = 6.34)

If you want to complete this work in 4 days (Skilled labor 4.3/4 = 1.1, Unskilled labor 12.68/3 = 4.22 MD)

 

Step 4: Calculation of Water:

Water for Mortar = 45 Lit/Cum, 8.75 x 45 = 394 Liter

 

Step 5: Calculation of Price:

 

No

Description

Quantity

Unit

Unit price

Total Price

1

Total Dry Volume - Bricks

3893

each

0.05 US$

194.65 US$

2

Total Cement

9

Big

6.4 US$

57.6 US$

3

Total Sand

1.87

Cum

4.5 US$

8.415 US$

4

Total Skilled labor

4.6

Person

13 US$

59.8 US$

5

Total Unskilled Labor

12.68

Person

5 US$

63.4 US$

6

Total required water

394

liter

0.012 US$

4.728 US$

Total Price

389 US$

 

According to your site location you can change the unit price.