Estimation of Stone Masonry work (Calculation of construction Materials, Water, Time, Labor, price)


 

Example: Find the price and construction materials Quantity for a stone masonry wall that has 50 meters length, 0.6 m width, and 2m height. The mixture ratio is (1: 4).

More Information about site location:

The price of one cubic meter of Stone is: 11 USD.

The price of one cubic Sand is: 6.4 USD.

The price of 1 bag Cement is: 4.5 USD.

The price of one liter of water is 0.001 USD.

Wage for Unskilled labor, 5 USD

Wage Skilled labor 13 USD

 Solutions:

 Step 1: Calculation of construction material:

Total Volume of Stone masonry (V) => V=Length x width x hight = L x W x H =    50 x 0.6 x 2= 60 Cubic meter.

For one cubic meter, 35% of the concrete mixture considered.

Concrete mixture (V1) => V1= 60 x 35%) = 21 m3

Dry Stone (V2) => V2 = 60-21=39 m3

Concrete mixture ratio is 1:4 (1-part cement + 4-part sand/gravel) 1+4 = 5 & Total concrete volume = 21 m3, (for dry Volume = V1 x 1.53) = 21 x 1.53 = 32.13

Total Cement: 32.13/5 x 1 = 6.42 m3 Cement, Density of cement = 1440 kg/ m³

=>> 6.42 x 1440 = 9244.8 Kg. 1 big cement = 50 Kg, 9244.8/50 = 185 Big.

Total Sand/gravel: 32.13/5 x 4 = 26 m3

(Construction Materials: Dry stone 39 m3, Cement 185 Bigs, Sand 26 m3)


 Step 2: Calculation of Skilled & Unskilled labor:

Unskilled labor (Worker): For 1 Cubic meter Stone 1.2 worker considered, Total worker for 60 Cum Stone Masonry= 60 x 1.2 = 72 unskilled workers.
Skilled labor (Worker): For 1 Cubic meter Stone 0.6 Skilled worker considered, Total worker for 60 Cum Stone Masonry= 60 x 0.6 = 36 skilled workers.


 Step 3: Calculation of water:

For one cubic meter stone masonry 72 lit water considered.

Total water required: 72 x 60 = 4320 lit


 Step 4: Price Calculation:

 

No

Description

Quantity

Unit

Unit price

Total Price

1

Total Dry Volume - Stone

39

Cum

11 US$

429 US$

2

Total Cement

185

Big

6.4 US$

1,184 US$

3

Total Sand/Gravel

26

Cum

4.5 US$

117 US$

4

Total Skilled labor

36

Person

13 US$

468 US$

5

Total Unskilled Labor

72

Person

5 US$

360 US$

6

Total required water

4320

liter

0.012 US$

51.84 US$

Total Price

2,609.84 US$

 